Bayes Questions

post by Bucky · 2018-11-07T16:54:38.800Z · LW · GW · 13 comments

For the first time ever I’ve had reason to use formal Bayesian statistics in my work. I feel this is a cause for streamers and confetti.

However, I’ve got a bit stuck on analysing my confidence levels and I thought what better place than lesswrong to check that I’m making sense. I’m not sure this is strictly what lesswrong is for but the site says that this is my own personal blog so I guess its ok?! I can always be down-voted to hell if not!

***

I’m trying to calculate estimated life before failure of a particular component.

We’ve done a number of tests and the results show a larger than expected variance with some components not failing even after an extended lifetime. I’m trying to analyse the results to see which probabilistic failure distribution best suits the available data. I have three different distributions (Weibull, Log-normal & Birnbaum-Saunders) each of which has a shape parameter and a scale parameter.

For each distribution I created a grid which samples the possible values of these parameters. I’ve given the parameters a log uniform prior by giving each sampled parameter pair a uniform prior but sampling the parameters geometrically (i.e. each sampled value of the parameter is a fixed multiple of the previous value). I’ve tried other priors and the results seem fairly robust over choice of prior.

For components which have failed, P(E|H) is the probability density function at the number of hours before failure.

For components which get to a certain age and do not fail, P(E|H) is 1 – the cumulative probability function at this number of hours.

This is implemented on a spreadsheet with a tab for each test result. It updates the prior probability into a posterior probability and then uses this as the prior for the next tab. The result is normalised to give total probability of 1.

Initially I calculate the expected life of the worst component in 1,000,000. For this, I just use the inverse cumulative probability function with p=0.000001 and calculate this for all of the potential probability distributions.

The results of this calculation are multiplied by the final probabilities of each distribution being the correct one. Then I sum this over the entire hypothesis space to give the expected life of the worst component in a million.

So my first question – is all of the above sound or have I made some silly mistake in my logic?

***

The part that I’m less confident about is how to analyse my 95% confidence level of the life of the worst component in 1,000,000.

The obvious way to approach this is that I should just calculate my expected value for the worst component in 20,000,000. Then, for any given million that I select, I have a 5% chance of selecting the worst in 20,000,000. This is treating 95% as my confidence from the overall weighted model.

Alternatively, I can treat the 95% as referring to my confidence in which is the one correct probability distribution. In this case, after I normalise my probabilities so that the sum of all of the hypotheses is 1, I start deleting the least likely hypotheses. I keep deleting unlikely hypotheses until the sum of all of the remaining hypotheses is <0.95. The last hypothesis which was deleted is the top end of my 95% confidence level.

Now if I calculate the expected life of the worst component in 1,000,000 for that individual model I think I can argue that this also represents my 95% confidence level of the worst component in 1,000,000 but in a different way.

Is either of these better than the other? Is there an alternative definition of confidence level which I should be using?

The confidence-in-which-distribution version gives much more conservative answers, particularly when the number of tests is small; the confidence-from-overall-model is much more forgiving of having fewer tests. Even after only a couple of tests the latter gives a 95% confidence level relatively close to the expected value, whereas the confidence-in-which-distribution version remains further away from the expected value until a larger number of tests is performed.

This seems to me to be more realistic but I don’t have a proper argument to actually justify a decision either way.

Any help warmly welcomed.

13 comments

Comments sorted by top scores.

comment by johnswentworth · 2018-11-07T18:40:57.792Z · LW(p) · GW(p)

I'll walk through how I'd analyze this problem, let me know if I haven't answered your questions by the end.

First, problem structure. You have three unknowns, which you want to estimate from the data: a shape parameter, a scale parameter, and an indicator of which model is correct.

"Which model is correct" is probably easiest to start with. I'm not completely sure that I've followed what your spreadsheet is doing, but if I understand correctly, then that's probably an overly-complicated way to tackle the problem. You want , which will be determined via Bayes' Rule by and your prior probability for each model being correct. The prior is unlikely to matter much unless your dataset is tiny, so is the important part. That's an integral:

In your case, you're approximating that integral with a grid over and ( is a shorthand for here). Rather than whatever you're doing with timesteps, you can probably just take the product of , where is the lifetime of the component in your dataset, then sum over the grid. (If you are dealing with online data streaming in, then you would need to do the timestep thing.)

That takes care of the model part. Once that's done, you'll probably find that one model is like a gazillion times more likely than the other two, and you can just throw out the other two.

On to the 95% CI for the worst part in a million.

The distribution you're interested in here is . is an order statistic. Its CDF is basically the CDF for any old point raised to the power of 1000000; read up on it to see exactly what expression to use. So if we wanted to do this analytically, we'd first compute via Bayes' Rule:

... where both pieces on the right would involve our integral from earlier. Basically, you imagine adding one more point to the dataset and see what that would do to . If we had a closed-form expression for that distribution, then we could just raise the CDF to the millionth power, we'd get a closed-form expression for the millionth order statistic, and from there we'd get a 95% CI in the usual way.

In practice, that's probably difficult, so let's talk about how to approximate it numerically.

First, the order statistic part. As long as we can sample from the posterior distribution , that part's easy: generate a million samples of , take the worst, and you have a sample of . Repeat that process a bunch of times to compute the 95% CI. (This is not the same as the worst component in 20M, but it's not any harder to code up.)

Next, the posterior distribution for . This is going to be driven by two pieces: uncertainty in the parameters and , and random noise from the distribution itself. If the dataset is large enough, then the uncertainty in and will be small, so the distribution itself will be the dominant term. In that case, we can just find the best-fit (i.e. maximum a-posteriori) estimates of and , and then declare that is approximately the standard distribution (Weibull, log-normal, etc) with those exact parameters. Presumably we can sample from any of those distributions with known parameters, so we go do the order statistic part and we're done.

If the uncertainty in and is not small enough to ignore, then the problem gets more complicated - we'll need to sample from the posterior distribution . At that point we're in the land of Laplace approximation and MCMC and all that jazz; I'm not going to walk through it here, because this comment is already really long.

So one last thing to wrap it up. I wrote all that out because it's a great example problem of how to Bayes, but there's still a big problem at the model level: the lifetime of the millionth-worst component is probably driven by qualitatively different processes than the vast majority of other components. If some weird thing happens one time in 10000, and causes problems in the components, then a best-fit model of the whole dataset probably won't pick it up at all. Nice-looking distributions like Weibull or log-normal just aren't good at modelling two qualitatively different behaviors mixed into the same dataset. There's probably some standard formal way of dealing with this kind of thing - I hear that "Rare Event Modelling" is a thing, although I know nothing about it - but the fundamental problem is just getting any relevant data at all. If we only have a hundred thousand data points, and we think that millionth-worst is driven by qualitatively different processes, then we have zero data on the millionth-worst, full stop. On the other hand, if we have a billion data points, then we can just throw out all but the worst few thousand and analyse only those.

Replies from: Bucky
comment by Bucky · 2018-11-07T22:50:25.646Z · LW(p) · GW(p)

Thanks John, that’s just the kind of thing I was hoping for.

The point about behaviour for the very worst components not following the same distribution as the population which I’m studying is a very good one.

I should have given a little more background to the task.

Firstly, the task is to compare a new component with an old one. Data is available for the old one and data is being collected for the new one. The new one has much higher average life but also much higher variance between samples which led to the question as to which will have the worst one-in-a-million performance.

Secondly, the number of data points is very small. Time cost per data point is ~1 week. I’ll be lucky if I have 10 data points in total. Essentially, I’m tasked to try to approve the component with the fewest possible data points.

(This means that so far I don’t have a favoured model (although Weibull is lower than the other 2) and I also don’t have a firm impression of μ and σ.)

I guess all I can achieve with limited data is to say that for components which fit the typical failure mechanism the worst one-in-a-million is better for the new component than the old. However, we don’t have any information on Black Swan events caused by a different failure mechanism for either component and I definitely need to make this clear in any presentation I make on the subject. With such a lack of data points I don’t think I can use rare event modelling to fill in the gaps.

I will have a look at the ideas about:

1. Taking multiple random samples of a million to get a better estimate of CI. I’m pretty sure this is comfortably within my limited programming skills.

(My limited programming skills are the main reason that my method is a bit long winded – doing it step by step was my way of trying to stop myself making a mistake which I didn’t notice. I did make a mistake with my application of the scale parameter for Birnbaum-Saunders at one point which this method helped me spot.)

2. Looking at how adding extra data points affects my result. I think I can use this to compare value of information with cost of information to get a good impression of when we have enough.

Replies from: johnswentworth
comment by johnswentworth · 2018-11-08T00:22:08.891Z · LW(p) · GW(p)

Having ~ten data points makes this way more interesting. That's exactly the kind of problem that I specialize in.

For the log-normal distribution, it should be possible to do the integral for explicitly. The integral is tractable for the normal distribution - it comes out proportional to a power of the sample variance - so just log-transform the data and use that. If you write down the integral for normal-distributed data explicitly and plug it into wolframalpha or something, it should be able to handle it. That would circumvent needing to sample and .

I don't know if there's a corresponding closed form for Birnbaum-Saunders; I had never even heard of it before this. The problem is still sufficiently low-dimensional that it would definitely be tractable computationally, but it would probably be a fair bit of work to code.

Replies from: habryka4, Bucky
comment by habryka (habryka4) · 2018-11-08T02:29:18.226Z · LW(p) · GW(p)

(I thoroughly enjoy/enjoyed this exchange and think I learned some things from it, and wanted to thank you for having this out in the open)

comment by Bucky · 2018-11-09T12:10:36.276Z · LW(p) · GW(p)

Birnbaum-Saunders is an interesting one. For the purposes of fatigue analysis, the assumptions which bring about the three models are:

Weibull - numerous failure modes (of similar failure speed) racing to see which causes the component to fail first

Log-normal - Damage per cycle is proportional to current damage

Birnbaum-Saunders - Damage per cycle is normally distributed and independent of previous damage

My engineering gut says that this component is probably somewhere between Log-normal and Birnbaum-Saunders (I think proportionality will decay as damage increases) which is maybe why I don't have a clear winner yet.

***

I think I understand now where my original reasoning was incorrect when I was calculating the expected worst in a million. I was just calculating worst in a million for each model and taking a weighted average of the answers. This meant that bad values from the outlier potential pdfs were massively suppressed.

I've done some sampling of the worst in a million by repeatedly creating 2 random numbers from 0 to 1. I use the first to select a μ,σ combination based on the posterior for each pair. I use the second random number as a p-value. I then icdf those values to get an x.

Is this an ok sampling method? I'm not sure if I'm missing something or should be using MCMC. I definitely need to read up on this stuff!

The worst in a million is currently dominated by those occasions where the probability distribution is an outlier. In those cases the p-value doesn't need to be particularly extreme to achieve low x.

I think my initial estimates were based either mainly on uncertainty in p or mainly on uncertainty in μ,σ. The sampling method allows me to account for uncertainty in both which definitely makes more sense. The model seems to react sensibly when I add potential new data so I think I can assess much better now how many data points I require.

Replies from: johnswentworth
comment by johnswentworth · 2018-11-09T19:12:09.424Z · LW(p) · GW(p)

That sampling method sounds like it should work, assuming it's all implemented correctly (not sure what method you're using to sample from the posterior distribution of , ).

Worst case in a million being dominated by parameter uncertainty definitely makes sense, given the small sample size and the rate at which those distributions fall off.

Replies from: Bucky
comment by Bucky · 2018-11-09T20:14:19.349Z · LW(p) · GW(p)

For μ,σ I effectively created a quasi-cumulative distribution with the parameter pairs as the x-axis.

μ1,σ1. μ2,σ1. μ3,σ1 ... μ1,σ2. μ2,σ2. μ3,σ2 ... μn,σm

The random number defines the relevant point on the y-axis. From there I get the corresponding μ,σ pair from the x-axis.

If this method works I’ll probably have to code the whole thing instead of using a spreadsheet as I don’t have nearly enough μ,σ values to get a good answer currently.

Replies from: johnswentworth
comment by johnswentworth · 2018-11-09T22:30:07.787Z · LW(p) · GW(p)

At what point is the data used?

Replies from: Bucky
comment by Bucky · 2018-11-09T22:44:04.817Z · LW(p) · GW(p)

I use it to determine the relative probabilities of each μ,σ pair which in turn create the pseudo cdf.

Replies from: johnswentworth
comment by johnswentworth · 2018-11-09T22:49:21.641Z · LW(p) · GW(p)

Ok, that sounds right.

comment by Dr_Manhattan · 2018-11-07T17:38:22.023Z · LW(p) · GW(p)

Can you program? In that case I highly recommend using PyMC or Stan for this kind of work. There's a pretty rich literature and culture of how to iteratively improve these types of models, and some tool support around these specific toolkits.

Replies from: Bucky
comment by Bucky · 2018-11-07T22:55:49.635Z · LW(p) · GW(p)

I can (a bit).

I have good programming skills compared to a typical mechanical engineer but poor compared to a typical programmer.

Is there any introductory text on the theory which you would recommend (forgetting about the programming for the moment)? I wouldn't want to try to use a programming language where I didn't understand the theory behind what I was asking the program to do.

Replies from: Dr_Manhattan
comment by Dr_Manhattan · 2018-11-08T13:50:53.710Z · LW(p) · GW(p)

The technologies I'm suggesting are just implementations of Bayes, which is what you're trying to do. There's some theory as to *how* they do inference (special versions of MCMC basically), but this is an "implementation detail" to a degree. Here's some references to get you started, though they're mostly Stan-centered http://mc-stan.org/users/documentation/external.html . If you want a better overall picture of the theory I really like this https://ben-lambert.com/a-students-guide-to-bayesian-statistics/ book, takes you from basics all the way to Stan usage